Carnival Takes Delivery of the LNG-Powered Mardi Gras

Caribbean News…
19 December 2020 7:28pm
Mardi Gras

Finnish shipbuilder Meyer Turku has delivered Mardi Gras, a 180, 000 gross tonnage, LNG-powered cruise ship, to the world’s largest cruise ship operator Carnival Cruise Line.

The shipbuilder sees the delivery as a major milestone having in mind the actual circumstances of the COVID-19 crisis.

Namely, the delivery of the 5,200-passenger ship was delayed on several occasions, due to the COVID-19 impact on the cruise and the shipbuilding industries.

“We are delivering a beautiful and highly advanced ship with world-class technology such as LNG propulsion, to name just one. With these sophisticated systems, she will be one of the most environmentally-friendly ships to sail the North-American waters. I am very proud of our team of shipbuilders and would like to thank everyone involved for their dedication during the building process”, CEO of Meyer Turku, Tim Meyer, said.

The delivery is being announced two months after the vessel completed her sea trials. The newbuild bears the same name as Carnival Cruise Line’s first ship launched in 1972.

At 180,000 tons, the 5,200-plus lower berth vessel will be more than six times the size of its namesake.

Mardi Gras has classical ship lines and a predominately-blue hull. The ship’s centerpiece is a three-stories-high atrium in the middle of the ship, opening up to a floor-to-ceiling window and movable LED screens.

Another marvel of the ship is of course Bolt, the first-ever roller coaster build on a ship. Bolt lets passengers do the driving with a top speed of 64km/h. Mardi Gras is planned to enter service from Port Canaveral, Florida in April 2021.

Source: Offshore Energy